Purpose of meeting:
- Set timelines
- Determine how much the build team can provide
Constraints:
- Initial launch of tools April 28
- Earlier launch required for UAT
- Earlier in April will need to deploy to Vegas DC for fanmail launch/testing
- April 7th or earlier – Anthill build script work is done, everything required for April 28 launch confirmed working.
Notes:
- Server is built: MS03
- Initial UAT will be used with test data on test server in Kelowna
- Dev is occurring on separate Dev servers (not in production). Tested and then branches are moved into Production.
- We need deployment – same as team.clubpenguin.com
- We have Ant script in progress, need to create automated build/deployment scripts.
- Nightly build vs. on demand? >> Use on demand for now.
- No problems/concerns with publishing/compiling with MS 03.
- Database is reaching capacity in sandbox. Chris to send helpdesk request for additional space.
- Need to determine if flex client and php server should run on same machine or separate. Should not be a problem to keep on same instance.
- Keith not here next week, but can spend much of his time on this in the short term.
Actions Items:
- Herman to create list of requirements to deploy on build server
- Joe/Keith: setup build server
- Joe: Need to replicate server access the current team has (TSS). Need to ask Disney – at least 1 week notice. For the web boxes, not the databases. Need to setup dual access/firewall holes.
- Chris to send Joe a list of services that need to talk to each other product (i.e. ToonTown).
- Joe to talk to TSS early about the services from other DOS products that need to talk to these boxes and vice versa (i.e. DISL).
- Joe/Gillian – is there a database setup for new customer service tools?
- Michael to follow up March 22nd to confirm everything is progressing appropriately (in addition to daily scrum updates).
- Watch item: There is an outstanding server request for new customer service tools . who do we talk to for new boxes for web servers: talk to Joe. Need to request a VM to get started. Needs to be in place by early april, make request in mid-march. Takes very little time to setup a VM.
Build script action items:
- Keith – review team project
- Keith – review existing customer service tools files
- Keith & Herman to work together to review setup and next steps; there are 2 parts that would need scripts: server side and flex
- Keith & Herman to build the scripts
- Keith & Herman to deploy to build server